Edgewater Infrastructure & Resilience Projects
City of Miami – District 2 Update
The City of Miami continues to advance several major infrastructure, flood mitigation, and pedestrian safety projects within Edgewater. Below is a summary of active and upcoming projects affecting our neighborhood, based on the City’s January 2026 District 2 Project Status Update.
Edgewater Flood Improvements – Phase I
Project ID: 40-B233805
This large-scale flood mitigation project is designed to reduce roadway flooding, improve stormwater capacity, and strengthen long-term resilience in Edgewater.
Scope of Work
- New and upsized stormwater pipes and inlets
- Lining of existing outfall pipes
- Construction of a stormwater pump station with injection wells
- Roadway reconstruction, milling, and resurfacing
- ADA ramps, signage, and pavement markings
Project Phasing
Due to funding constraints, the project is being delivered in two phases:
Phase 1
- NE 23 Street between NE 4 Avenue and Biscayne Bay
- NE 4 Avenue from NE 23 Street to NE 22 Terrace
Phase 2
- NE 22 Terrace between NE 4 Avenue and Biscayne Bay
- NE 22 Street between NE 4 Avenue and Biscayne Bay
- NE 4 Avenue between NE 24 Street and NE 23 Street
- NE 4 Avenue between NE 22 Terrace and NE 22 Street
Status & Timeline
- Design-build project currently in the design phase
- Construction anticipated to begin July 2026
- Estimated completion October 2027
Funding Notes
- Combination of Miami Forever Bond and federal/state grants
- Portions of federal funding are at risk due to strict completion deadlines
Replacement of Eight Seawalls in Edgewater
Project ID: 40-B233810
This project focuses on replacing aging seawalls along Biscayne Bay to protect public infrastructure and improve coastal resilience.
Locations Included
- NE 22 Street
- NE 22 Terrace
- NE 25 Street
- NE 26 Street
- NE 27 Street
- NE 30 Street
- NE 30 Terrace
- NE 35 Street
(All along Biscayne Bay)
Scope of Work
- Seawall replacement or elevation
- Installation of tidal valves and manatee grates
- Riprap installation and outfall improvements
- Roadway milling, resurfacing, lighting, and landscaping
Status & Timeline
- Project currently in design
- Updated design resubmittals expected early 2026
- Construction anticipated February 2027 through February 2028
Permitting
- Multiple permits under active review with DERM, FDEP, and USACE
- Coral relocation plans required for select locations
Citywide Tidal Valve Installations (Edgewater Locations)
Project ID: 40-B233806
As part of the City’s Sea Level Rise Resilience Plan, tidal valves are being installed to prevent seawater from entering stormwater systems during high tide events.
Edgewater-Area Installation Sites
- 777 NE 26 Street
- 127 N. Bayshore Drive at NE 21 Street
- NE 31 Street east of NE 7 Avenue
- 2123 N. Bayshore Drive
- 1803 N. Bayshore Drive
Status
- Design phase underway
- Valves are being procured for phased installation
- Construction will occur under an existing citywide stormwater contract to accelerate delivery
Pedestrian Safety & Traffic Calming
North Bayshore Drive Traffic Circle
Project ID: 40-B203614
A new traffic circle is being constructed to improve pedestrian safety and traffic flow along North Bayshore Drive.
Location
- North Bayshore Drive between NE 15 Street and NE 17 Terrace
Improvements Include
- Traffic circle installation
- Sidewalk and ADA ramp upgrades
- Drainage improvements
- Landscaping and lighting enhancements
Status & Timeline
- Construction began February 2026
- Estimated completion September 2026
- Groundbreaking ceremony scheduled for March 2, 2026
Funding
- Supported by the Omni CRA
- Additional City and CITT funding allocated to support completion
What This Means for Edgewater Residents
These projects represent significant investment in flood protection, roadway safety, and long-term climate resilience for Edgewater. While construction activity may cause temporary disruptions, these improvements are designed to protect property, improve mobility, and strengthen the neighborhood’s infrastructure for decades to come.
Updates will continue to be shared as projects advance.
Source: City of Miami District 2 – January 2026 Project Status Update (Pages 19–21, 25–27, 31–34)